The Algerian Minister of Public Works and Basic Infrastructure, Abdelkader Djellaoui, carried out on Sunday an inspection visit to the construction site of Hammaguir-Abadla section, a key component of Bechar-Tindouf-Gara Djebilet railway megaproject, whose total length reaches 950 km.
During his visit, the minister noted the sustained pace of work on engineering structures and rail laying. Of the 120 km of the Hammaguir-Abadla section, almost all the engineering structures are completed, while rail laying progresses at a daily rate of 10 km.
According to Abdelchafi Benrabia, the project’s director, 800 kilometers of track have been installed and approved along the 950-kilometer line.
The remaining 150 kilometers should be completed by December 20, enabling the delivery of the entire project within the same deadlines.
Accompanied by local authorities, Djellaoui also visited the construction site of the future Hammaguir station, currently in the finalization phase.
He praised the chosen architectural design, conceived to accommodate passengers, manage goods and facilitate the transit of mining trains.